3V0-624 (Question 56)

DRAG DROP

A company has one data center site running 50 hosts and 400 virtual machines and requires a vSphere 6.x design.

  1. The CIO wants to add a secondary site for Disaster Recovery (DR) with 4 hours RPO.
  2. The application developer is concerned about anticipated growth as several new project begin.
  3. The CISO is worried about data leaks and theft.
  4. The CTO would like to buy new servers with better specifications and higher consolidation ratio.

Determine the critical requirements for each of the key stakeholders. Some requirements might have more than one stakeholder.

Select and Place:

Correct Answer:

Paylaş:
ÖNCEKİ YAZI
3V0-624 (Question 55)
SONRAKİ GÖNDERİ
3V0-624 (Question 57)